Receipt of an appeal to JSC Tula region development corporation
Sending an appeal to the Ministry of Economic Development of the Tula Region
1 day
The deputy director-head of the department
- enters the appeal in the journal of investor requests
- determines the responsible official to assess the content of the appeals
2 days
An official conducts a comprehensive study of the legislation in order to establish signs of a violation (if no signs are identified, the appeal is considered in accordance with the instructions for office work approved by the Decree of the Governor of the Tula Region on August 24, 2012 No. 103)
In case of revealing signs of a violation of the law, the official sends a request to the appropriate industry authority to eliminate violations of the law
1 day
The responsible official notifies the investor about the direction of his appeal for consideration to the industry authority
1 day
The responsible official draws up an action plan to promptly eliminate violations of the law, indicating the stages, deadlines and persons responsible for its implementation
3 days
A working group is created if necessary. The total period for prompt elimination of violations of the law is no more than 20 days, except for cases requiring changes (development) in legal acts of the Tula region
The responsible official notifies the investor about the results of the elimination of the violation of the law
1 day